Roadmap that outlines when results submission related tasks, and deadlines are expected to be completed.
Verification Round 1
Activity
Date
Status
Counties submission deadline for Verification Round 1
31 March 2025
Ongoing
Counties due to hear back from PMU on Results Verified
29 June 2025
Ongoing
Counties receive disbursement against verification RVR 1
28 February 2026
Upcoming
Verification Round 2
Activity
Date
Status
Counties submission deadline for Verification Round 2
25 July 2026
Upcoming
Counties due to hear back from PMU on Results Verified
31 August 2026
Upcoming
Counties receive disbursement against verification RVR 2
15 October 2026
Upcoming